These 64 time points, engineering people need to understand

Hits : Update:2019-03-15 10:58

Relevant time for bidding

1. Deadline for submission of bids: Valid for ≧20 days.

2. Modification of the bidding documents: 15 days before the submission of the bidding documents.

3. Survey site: 1~2 days before the tender preparation meeting.

4. Preparation for the tender: 7~28 days after the issuance of the bidding documents.

5. When the bidder finds that the bidding documents are in error, it shall indicate in writing within 7 days of receiving the bidding documents.

6. Return the bid bond: 14 days after the expiration of the bid, within 5 days after the contract is booked.

7. The bid bond issued by the bank or the guarantee company shall continue to be valid within 28 days after the expiration of the bid.

8. The bid evaluation and calibration shall be completed 30 working days before the end of the bid validity period.

9. Submit the bidding report within 15 days after the successful bidder is confirmed.

10. Sign the contract within 30 days from the issuance of the bid winning notice.

11. Within 7 days after the conclusion of the contract, the construction administrative department shall file the record.

Relevant time during the performance of the contract

12. The contractor shall replace the representative and notify the contractor in writing at least 7 days in advance.

13. The engineer's verbal instructions are confirmed in writing within 48 hours. If it cannot be confirmed in writing, the contractor shall submit a written confirmation request within 7 days after the oral instruction. This request shall be answered within 48 hours. If it is not given, it shall be confirmed.

14. The contractor cannot start work according to the agreed date. The contractor shall explain the reason at least 7 days in advance. The engineer will reply within 48 hours after receiving the application for extension, and shall not agree to the written reply.

15. The engineer shall report the engineer in writing within 14 days after the occurrence of the delay.

16. The engineer cannot participate in the acceptance on time. The extension request must be submitted to the contractor 24 hours before the acceptance. The extension cannot exceed 2 days.

17. The contractor reports the engineer within 14 days after the price adjustment can be made.

18. The payment is requested from the contractor within 7 days after the agreed payment time.

19. The engineer will verify within 7 days after receiving the completed project report and notify the contractor 24 hours before the verification.

20. Progress payment: The project payment will be paid to the contractor within 14 days after the measurement is confirmed.

21. The contractor shall organize the acceptance within 28 days after receiving the completion acceptance report and give approval within 14 days after the acceptance.

22. Within 28 days after the approval of the completion acceptance report, the contractor submits the completion settlement report and complete information to the contractor, and the contractor verifies the settlement price within 28 days to confirm the settlement price.

23. Within 14 days after the contractor receives the settlement payment, the completed project will be handed over to the contractor.

24. The warranty will be refunded within 14 days after the warranty period expires.

Change the time associated with the claim

25. A report on the change of the project price within 14 days after the change event is confirmed within 7 days. When there is no reason to confirm, it will take effect after 14 days from the report.

26. Within 28 days after the claim time, the notice of intention of the claim will be issued, and the relevant information will be submitted within 28 days, and the engineer will reply within 28 days. If it is not answered, it is considered as approval. In the case of consecutive incidents, the intention of claim is submitted in stages, and the final claim report is submitted within 28 days after the end.

Relevant time under FIDIC contract conditions

27. The verbal instructions of the engineer shall reply within 2 days after receiving the written confirmation from the contractor, and the written order shall be changed to a written order.

28. The owner replacement engineer must notify the contractor 42 days in advance.

29. The contractor submits a performance guarantee to the owner within 28 days after receiving the letter of acceptance.

30. The owner will return the performance guarantee to the contractor within 21 days after receiving the copy of the performance guarantee certificate.

31. The contractor started work within 42 days after receiving the letter of acceptance.

32. The engineer will issue a notice of commencement of work 7 days before the start date.

33. The contractor submits a detailed schedule to the engineer within 28 days after receiving the notice of commencement of work.

34. After the performance bond and the payment guarantee letter are given to the engineer, the engineer will issue a notice of payment to the payment within 21 days.

35. Progress payment: The payment certificate will be issued within 28 days after receiving the contractor's payment report.

36. The owner's payment progress shall not exceed 56 days after the engineer receives the contractor's monthly progress payment request.

37. Completion inspection: The contractor shall notify the engineer 21 days in advance of the date, and the engineer shall conduct it within 14 days after the date.

38. Receiving card: After the basic completion requirements are met, the engineer will be required to apply for the issuance of the engineering acceptance certificate in writing 14 days before the handover can be completed. Engineers are issued within 28 days of this application.

39. Completion settlement: Within 84 days after the issuance of the project acceptance certificate, the contractor shall report the completion report, the visa within 28 days, and pay the settlement payment.

40. Within 28 days after the expiration of the defect notification period, the engineer issues a certificate to the owner to release the contractor’s responsibility for the engineering defect and issue a performance certificate. The owner refunds the performance bond within 14 days after the certificate method

41. Final settlement: Within 56 days after the performance certificate is issued, the contractor submits the settlement statement. The engineer signs the payment certificate within 28 days and pays within 56 days after receiving the certificate.

42. The engineer decides on the dispute: the decision will be notified to both parties within 84 days. If the parties have not submitted the notice of arbitration after 70 days, the decision is final.

43. Decision of the Dispute Adjudication Board: The decision shall be made within 84 days after receiving the written report. If it is not satisfied, the dissatisfaction notice will be sent to the other party within 28 days and submitted to the arbitration.

44. Arbitration must be filed 56 days after the decision of the adjudication committee.



Relevant time of the accident

45. Safety production accidents: After receiving the report, the person in charge of the unit shall report to the government safety supervision department at the county level or above and relevant departments within one hour.

46. Time for safety and safety accidents The safety supervision department reports step by step: 2 hours.

47. Quality accidents occurred in the construction project: The relevant units shall report to the local construction administrative department and other relevant departments within 24 hours.

48. Production safety accident replenishment time: Road traffic accidents, fire accidents, replenishment within 7 days, general accidents within 30 days.

49. Time limit for accident handling: Extraordinary accident: 30 days; Other: 15 days; Up to 30 days.

50. Accident investigation period: The accident investigation report shall be submitted within 60 days from the date of the accident; the maximum length may be extended by 60 days.



Laborer's relevant time

51. Overtime time limit: generally no more than 1 hour per day; special reasons shall not exceed 3 hours per day under the conditions of ensuring the health of workers, but shall not exceed 36 hours per month.

52. Part-time employment: Generally, the average daily working time does not exceed 4 hours, and the accumulated weekly time does not exceed 24 hours.

53. The settlement period for part-time employment labor compensation shall not exceed 15 days.

54. Trial period: fixed period of more than three years and no fixed period: no more than 6 months.

55. A written labor contract shall be concluded within one month from the date of employment.

56. Dismissing the labor contract: The laborer can notify the employer to terminate the labor contract three days before the trial period. After the transfer is completed, the employer must notify the employer in writing to terminate the labor contract 30 days in advance.

57. Economic layoffs: Explain the situation to the trade union or all employees 30 days in advance, and listen to the opinions of the trade unions or employees. If the personnel are re-employed within six months, the personnel who have been laid off will be given priority under the same conditions.

58. Do not extend working hours and night work: 7 months or more of pregnancy and lactation.

59. More than one month but less than one year from the date of self-employment: pay twice the monthly salary to the laborer.

60. One year from the date of self-employment: It is considered that the employer and the employee have entered into a non-fixed-term labor contract.

61. The time for the worker to apply for work injury identification: 1 year.

62. Employer (labor dispatching unit): The labor dispatching unit shall conclude a fixed-term labor contract with the dispatched laborer for more than two years.

63. The case should be concluded without a fixed-term labor contract. (1) The laborer has been working continuously for ten years in the employer; (2) When the employer first implements the labor contract system or the state-owned enterprise reforms and re-enters the labor contract, the laborer is The employer has worked continuously for ten years and is less than ten years from the statutory retirement age.

64. If the monthly salary of the employee is higher than three times the average monthly salary of the employee in the previous year, the municipal-level people's government of the district where the employer is located, the standard for paying the economic compensation to the employer shall be three times the average monthly salary of the employee. The maximum period of payment of economic compensation to it is no more than twelve years.